68
There was a preliminary activity followed by site inspection and preparation
of program of work. The staff of NCIP-Tinglayan CSC administered the purchase
and delivery of materials needed. Laborers were hired for the fencing of the
garden, and collecting and transplanting the herbal plants.
Problems encountered were miscalculation of the purchase materials due
to non-inclusion of some needed materials during the preparation of detailed cost
estimate and program of work hence emergency purchase of lacking materials
done adhering to procurement guidelines.
For the sustainability of the project, partnership with beneficiaries and LGUs
is recommended at the same time, funds for maintenance should be allotted in the
future.
4. Collaboration and Coordination with other Agencies/Sectors
Region
11
12
Total
Particulars
Support
to
IP-MNCHN
Implementation for Davao
Region
Strengthening Access to IP
Health Programs
Project
Cost
318,000
No. of projects
implemented
1
No. of IP
beneficiaries
1429
106,000
1
25
424,000
2
1454
Region 11 implemented Support to IP-MNCHN Project for Davao Region
(2018) Region wide with a cost of 318,000.00. Activities undertaken were
a. Training on the Proper Identification and Use of Herbal Medicinal Plants,
Soap Preparation and Body Hygiene/Acupressure. This was done in
partnership with Philippine Institute on Traditional and Alternative Health
Care(PITAHC). There were One Hundred Fifty-Eight (158) IP women
trained in four (4) different venues on the proper identification and use
of herbal medicines. In addition, they were also taught on how to prepare
soap, ointment for skin allergies, simple body hygiene, basic massage
and acupressure.
b. IEC on JMC and Culture – Sensitivity Orientation which included series
of advocacy activities and culture – sensitivity orientation conducted to