Land Acquisition, Resettlement and Rehabilitation Policy, 3rd edition (2006)
The tasks of the Internal Monitoring Agent are to:
a. Regularly supervise and monitor the implementation of the RAPs and IPAPs (for
those affected IPs living outside ancestral domains) in coordination with the
concerned District Engineering Office (DEO), Regional Office (RO), and the
Resettlement Implementation Committee (RIC). The findings will be
documented in the quarterly report to be submitted to the PMO, which in turn will
submit the report to the Bank;
b. Coordinate with the NCIP regarding the monitoring and evaluation of the
situation of affected IP communities, inside or outside ancestral domains;
c. Coordinate with the NCIP and the affected IP community in the monitoring and
evaluation of the MOA;
d. Verify that the re-inventory baseline information of all PAFs has been carried out
and that the valuation of assets lost or damaged, the provision of compensation
and other entitlements, and relocation, if any, has been carried out in accordance
with the LARRIPP and the respective RAP Reports;
e. Ensure that the RAPs, IPAPs, and (with the NCIP and the affected IP
communities) the MOA are implemented as designed and planned;
f. Verify that funds for implementing the RAPs, MOA, and IPAPs are provided by
the PMO in a timely manner and in amounts sufficient for the purpose;
g. Record all grievances and their resolution and ensure that complaints are dealt
with promptly;
h. With the relevant branch of the NCIP and the MRIC, monitor the implementation
of IPAPs covering affected IP communities living outside ancestral domains.
2. Monitoring of MOA with Affected IPs inside Ancestral Domains
The procedure for monitoring Memoranda of Agreement (MOA) that the project
proponent enters into with affected IPs inside Ancestral Domains will be guided by the
monitoring, evaluation, and reporting arrangements set forth in that MOA.
3. Monitoring of IPAPs for Affected IPs living outside Ancestral Domains
Environmental and Social Services Office
Department of Public Works and Highways
March 2006, Revised October 2006
41
Select target paragraph3
Connect to a paragraph
Connect to an entity
Disable highlights
Add to table of contents