RULE II
GENERAL RULES AND PROCEDURES IN THE SURVEYS OF ANCESTRAL LANDS AND
DOMAINS
A. PROCEDURES FOR THE SURVEYS OF ALs/ADs
Section 1. General Procedure. The survey of ADs/ALs covered by applications for the issuance
of CADT/CALT without an approved survey plan shall undergo the following procedures:
a.
Issuance of the Work Order/Authority to Survey and Notice to Proceed. The
RRB shall ensure substantial compliance with Part I, Rule IV, Section 14 of this Rules before the
issuance by the ADO Director of the Work Order/Survey Authority to the concerned geodetic
engineers/contractor geodetic engineer.
Work Order/Survey Authority may be issued by phase/stage of work such as but not limited to
establishment of project controls and perimeter survey.
Work Order/ Survey Authority shall be effective for a period of six (6) months from issuance and
may be renewed for the same period, provided however, that the authority shall be terminated as
soon as the project is completed.
Actual survey activities must only commence from the time the Notice to Proceed is duly issued.
The POs/ROs shall recommend to the ADO Director the composition of the Survey Party.
b.
Research/Data
Gathering.
The
Survey
Team
shall
collect
all
data/documents/materials that will facilitate the generation of the technical description of the
ancestral domain/land and Land Registration Authority requirements. Moreover, the Survey
Party must ensure that all survey related documents not forming part of those submitted by the
community/land owner/claimants must be researched and secured in order to facilitate the
delineation.
c.
Survey Notification. All stakeholders shall be notified of the intended survey in
accordance with Part I, Rule IV, Section 20 hereof using ADO Form No. 08. The notice, signed by
the COP and noted by the POr/CDO, shall state the date/s when the areas may be traversed by
the survey team, the names of the concerned Geodetic Engineers, and shall likewise state Section
56 of R.A. 8371.
d.
Mission Planning. During the Mission Planning, the Geodetic Engineer, together
with the PDT/CDT, shall discuss with the stakeholders the procedures involved in the survey
activity and their respective functions and responsibilities.
If the area to be surveyed is located next to another ancestral domain area, representatives from
the adjoining area shall be invited to attend the Mission Planning.
e.
Reconnaissance. A field reconnaissance shall be carried out by the Survey Team
prior to the survey in order to identify the location and existence of previously established
control/reference points and possible location of project control points to be established and
route for the survey.
f.
Establishment of Project Controls. In the establishment of project controls, the
Survey Team shall look for existing control/reference points within or near the ancestral
domain/land and thereafter establish new controls for the ancestral land/domain boundaries.
At least two (2) intervisible control points are necessary in the establishment of control points,
provided, that the distance to be maintained in between each pair of control points shall not be
less than one hundred (100) meters.
The survey of project control is made using survey grade
Global Positioning System (GPS) equipment or conventional survey instruments
The project control monuments shall be placed in pairs using standard concrete monuments
measuring 30 cm x 30 cm by 100 cm, set at 70 cm on the ground, centered by a galvanized iron
spike/copper nail. The label on top of the monument shall specify: (a) the name of the station,
which may be derived from the first three (3) letters of the province where it is located, subject to
the approval of ADO, numbered accordingly or in coordination with DENR-FNSP; (b) the year of
establishment; and, (c) the acronym of NCIP. These project controls are installed at an interval of
5 km distance.
Page 18 of 26
Revised Omnibus Rules on Delineation and Recognition of Ancestral Domains and Lands of 2012
Select target paragraph3
Connect to a paragraph
Connect to an entity
Disable highlights
Add to table of contents